June July August September October November December January February March April May June July


Posted August 24, 2011 Daily Report for Friday August 19, 2011

Continue grading and seeding/erosion controls in SWMU 5N and SWMU 7


Posted August 24, 2011 Daily Report for Thursday August 18, 2011

Continue grading and seeding/erosion controls in SWMU 5N and SWMU 7


Posted August 24, 2011 Daily Report for Wednesday August 17, 2011

Continue grading and seeding/erosion controls in SWMU 5N and SWMU 7


Posted August 19, 2011 Daily Report for Tuesday August 16, 2011

Continue grading and seeding/erosion controls in SWMU 5N and SWMU 7


Posted August 19, 2011 Daily Report for Monday August 15, 2011

Placement of erosion controls in SWMU 6; Continue grading SWMU 6 and SWMU 7;


Posted August 19, 2011 Daily Report for Saturday August 13, 2011

Continue placement of erosion controls in CAMU;


Posted August 19, 2011 Daily Report for Friday August 12, 2011

Continue seeding/erosion controls in CAMU; Final grading activities in SWMU 6 and SWMU 7; Reynolds completed cleaning and rehabilitation of SB7


Posted August 15, 2011 Daily Report for Thursday August 11, 2011

Continue seeding/erosion controls in CAMU; Final grading activities in SWMU 6 and SWMU 7;


Posted August 15, 2011 Daily Report for Wednesday August 10, 2011

Final grading activities in SWMU 6 and SWMU 7;


Posted August 15, 2011 Daily Report for Tuesday August 9, 2011

Opal, Western, and Envirocon prepare punch list for final walk through activities;


Posted August 15, 2011 Daily Report for Monday August 8, 2011

Continue seeding/ erosion/sediment control of CAMU surface and ditches;


Posted August 8, 2011 Daily Report for Saturday August 6, 2011

Continue seeding and erosion/sediment control mats at South End of CAMU;


Posted August 8, 2011 Daily Report for Friday August 5, 2011

Continue seeding and erosion/sediment control mats at South End of CAMU;


Posted August 5, 2011 Daily Report for Thursday August 4, 2011

Complete installation of culvert from EQB to Settling Basin;


Posted August 5, 2011 Daily Report for Wednesday August 3, 2011

Begin installation of culvert from EQB to Settling Basin; Begin installation of erosion control mats in CAMU ditches and seeding preparation


Posted August 3, 2011 Daily Report for Tuesday August 2, 2011

Continue installation of culverts at SW corner of CAMU;


Posted August 3, 2011 Daily Report for Monday August 1, 2011

Began Installation of culverts at SW corner of CAMU;


Posted August 3, 2011 Daily Report for Saturday July 30, 2011

Continued placement of topsoil on north half of CAMU;


Posted August 2, 2011 Daily Report for Friday July 29, 2011

Continued placement of topsoil on north half of CAMU;


Posted August 2, 2011 Daily Report for Thursday July 28, 2011

Continued placement of topsoil on north half of CAMU; Reynolds SB Rehab crew completed cleaning/rehab of SB35 and departed site until 8/8/11;


Posted August 2, 2011 Daily Report for Wednesday July 27, 2011

Continued placement of topsoil on north half of CAMU; Reynolds SB Rehab crew completed cleaning/rehab of SB42;


Posted August 2, 2011 Daily Report for Tuesday July 26, 2011

Began placement of topsoil on north half of CAMU; Reynolds SB Rehab crew completed cleaning/rehab of SB40;


Posted August 2, 2011 Daily Report for Monday July 25, 2011

Completed placement of VA#10 at north half of CAMU; Reynolds SB Rehab crew temporarily ceased rehab of SB7 and completed cleaning/rehab of SB59;


Posted July 26, 2011 Daily Report for Saturday July 23, 2011

Continued placement and grading of VA#10 at north half of CAMU; Reynolds Sewer Box Rehab crew continued rehab of SB7;


Posted July 26, 2011 Daily Report for Friday July 22, 2011

Continued placement and grading of VA#10 at north half of CAMU; Reynolds Sewer Box Rehab crew completed rehab of SB60;


Posted July 26, 2011 Daily Report for Thursday July 21, 2011

Continued placement and grading of VA#10 at north half of CAMU; Reynolds Sewer Box Rehab crew began cleaning SB60;


Posted July 25, 2011 Daily Report for Wednesday July 20, 2011

Continued placement and grading of VA#10 at north half of CAMU; Reynolds Sewer Box Rehab crew cleaned and rehabilitated ASB58 and SB58;


Posted July 25, 2011 Daily Report for Tuesday July 19, 2011

Continued placement and grading of VA#10 at north half of CAMU; Reynolds installed CIPP from SB59 to SB60;


Posted July 25, 2011 Daily Report for Monday July 18, 2011

Continued placement and grading of VA#10 at north half of CAMU; Reynolds installed CIPP from ASB58 through SB58 to SB59;


Posted July 19, 2011 Daily Report for Saturday July 16, 2011

Completed permanent stormwater culverts at NW corner of CAMU beneath Ave A; Reynolds cleaned and conducted Pre-CCTV from ASB58 to SB60;


Posted July 19, 2011 Daily Report for Friday July 15, 2011

AEGL completed CAP system with final installation of geocomposite; Reynolds lined SB5A to SB5B


Posted July 18, 2011 Daily Report for Thursday July 14, 2011

Begin installation of permanent stormwater culverts at NW corner of CAMU beneath Ave A;


Posted July 18, 2011 Daily Report for Wednesday July 13, 2011

Installed final 60 ml geomembrane panels at north edge of CAMU; Reynolds Inliner lined from Tk10 to SB1 and completed SB rehabilitation at Tk613 and SB38;


Posted July 18, 2011 Daily Report for Tuesday July 12, 2011

Resumed re-grading/drying material at north edge of CAMU; Reynolds Inliner lined from Tk613 to SB38 and finished rehab activities at SB6;


Posted July 18, 2011 Daily Report for Monday July 11, 2011

Continued to dewater work areas; Reynolds Inliner back onsite and cleaned/inpected Tk613 to SB38 for lining tomorrow;


Posted July 18, 2011 Daily Report for Sunday July 10, 2011

Continued to dewater work areas;


Posted July 18, 2011 Daily Report for Saturday July 9, 2011

Rain greater than 4" over last 24 hours; Dewatered work areas;


Posted July 13, 2011 Daily Report for Friday July 8, 2011

Installed 15,000 sqf of TN220 composite at north end of CAMU; CAMU 97% lined; Heavy rains forecasted;


Posted July 13, 2011 Daily Report for Thursday July 7, 2011

Installed 27,852 sqf of HDPE at north end of CAMU;


Posted July 13, 2011 Daily Report for Wednesday July 6, 2011

Heavy Rain; Continue to dewater, re-grade, and dry remaining waste surface for installation of remaining CAP;


Posted July 8, 2011 Daily Report for Tuesday July 5, 2011

Prepare waste surface (re-grade/dry) for installation of remaining CAP on former TSWRB (pending weather);


Posted July 8, 2011 Daily Report for Monday July 4, 2011

Rain; Limited Envirocon crew onsite to maintain dewatering pumps;


Posted July 8, 2011 Daily Report for Sunday July 3, 2011

Install geomembrane panels and geocomposite on former TSWRB to the extent conditions would allow;


Posted July 8, 2011 Daily Report for Saturday July 2, 2011

Install geomembrane panels on former TSWRB to the extent conditions would allow;


Posted July 8, 2011 Daily Report for Friday July 1, 2011

Prepare waste surface (re-grade/dry) for installation of CAP on former TSWRB;


Posted July 8, 2011 Daily Report for Thursday June 30, 2011

Installation of CAP at former TSWRB delayed due to wet conditions;


Posted July 8, 2011 Daily Report for Wednesday June 29, 2011

Installation of CAP at former TSWRB delayed due to wet conditions;


Posted July 1, 2011 Daily Report for Tuesday June 28, 2011

Installation of CAP at former TSWRB delayed due to heavy rain yesterday;


Posted July 1, 2011 Daily Report for Monday June 27, 2011

Installation of CAP at former TSWRB delayed due to heavy rain in early AM;


Posted June 30, 2011 Daily Report for Sunday June 26, 2011

Resumed installation of geomembrane cap at North end of CAMU; Reynolds Inliner installed CIPP from SB2 to SB1;


Posted June 30, 2011 Daily Report for Saturday June 25, 2011

Completed TSWRB closure and final grading at North end of CAMU; Reynolds Inliner conducted Post-CCTV from SB38 to SB40;


Posted June 29, 2011 Daily Report for Friday June 24, 2011

Continue TSWRB closure; Reynolds Inliner installed CIPP from SB38 to SB40;


Posted June 29, 2011 Daily Report for Thursday June 23, 2011

Continue TSWRB closure; Reynolds Inliner installed CIPP from Tk 900 to SB1 and from SB5A to SB5;


Posted June 27, 2011 Daily Report for Wednesday June 22, 2011

Continue TSWRB closure; Reynolds Inliner installed CIPP from SB14 to SB5B;


Posted June 27, 2011 Daily Report for Tuesday June 21, 2011

Continue installation of geosynthetic cap and TSWRB closure; Reynolds Inliner installed CIPP from SB18 to SB14;


Posted June 27, 2011 Daily Report for Monday June 20, 2011

Continue installation of geosynthetic cap and TSWRB closure; Reynolds Inliner back onsite and continued OWS CIR activities


Posted June 27, 2011 Daily Report for Saturday June 18, 2011

Limited crew grading waste and maintaining ditch pumps


Posted June 22, 2011 Daily Report for Friday June 17, 2011

Continue cap installation and closure of TSWRB


Posted June 22, 2011 Daily Report for Thursday June 16, 2011

Continue cap installation; Begin closure of TSWRB


Posted June 22, 2011 Daily Report for Wednesday June 15, 2011

Continue cap installation;


Posted June 17, 2011 Daily Report for Tuesday June 14, 2011

Continue cap installation; Continue OWS point repairs


Posted June 17, 2011 Daily Report for Monday June 13, 2011

Continue cap installation; Begin OWS point repairs


Posted June 16, 2011 Daily Report for Saturday June 11, 2011

Continue installation of geomembrane cap system; Reynolds offsite until 6/20/11


Posted June 16, 2011 Daily Report for Friday June 10, 2011

Complete excavation activities at SWMU 7; Reynolds offsite until 6/20/11


Posted June 16, 2011 Daily Report for Friday June 10, 2011

Complete excavation activities at SWMU 7; Reynolds offsite until 6/20/11


Posted June 16, 2011 Daily Report for Thursday June 09, 2011

Begin installation of geomembrane cap on North half of CAMU; Reynolds demobilized until 6/20/11


Posted June 16, 2011 Daily Report for Wednesday June 08, 2011

Continue excavation of area between SWRP and FBP; Reynolds installed CIPP from SB42 to Money Pit


Posted June 16, 2011 Daily Report for Tuesday June 07, 2011

Continue excavation of area between SWRP and FBP; Reynolds prepared to install CIPP from SB42 to Money Pit


Posted June 08, 2011 Daily Report for Monday June 06, 2011

Completing SWRP Areas 5/12 and begin area between SWRP and FBP; Reynolds installed CIPP from SB40 to Money Pit


Posted June 08, 2011 Daily Report for Saturday June 04, 2011

Continued excavation of SWRP Area 5; Reynolds installed CIPP from SB40 to SB37


Posted June 08, 2011 Daily Report for Friday June 03, 2011

Continued excavation of SWRP Area 5;


Posted June 06, 2011 Daily Report for Thursday June 02, 2011

Continued excavation of Area 12 and 5; Reynolds installed CIPP from SB35 to SB37;


Posted June 06, 2011 Daily Report for Wednesday June 01, 2011

Continued excavation of Area 12; Prepared to install CIPP from SB35 to SB37;


Posted June 06, 2011 Daily Report for Tuesday May 31, 2011

Continued excavation of Area 12; Reynolds installed 503' of 48" CIPP from SB10 to SB35;


Posted June 06, 2011 Daily Report for Sunday May 29, 2011

Maintained ditch pumps; Reynolds Inliner cut laterals for CIPP from SB7 to SB10;


Posted June 06, 2011 Daily Report for Saturday May 28, 2011

Maintained ditch pumps; Reynolds Inliner installed CIPP from SB7 to SB10;


Posted May 31, 2011 Daily Report for Friday May 27, 2011

Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed final CCTV and prepared for 48" CIPP installation from SB10 to SB7;


Posted May 31, 2011 Daily Report for Thursday May 26, 2011

Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed 36" CIPP installation from SB6 to SB7;


Posted May 31, 2011 Daily Report for Wednesday May 25, 2011

Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed final CCTV and prepared for 36" CIPP installation from SB6 to SB7;


Posted May 31, 2011 Daily Report for Tuesday May 24, 2011

Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed 21" CIPP installation from SB6 to SB3;


Posted May 31, 2011 Daily Report for Monday May 23, 2011

Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed final CCTV and prepared for 21" CIPP installation from SB6 to SB3;


Posted May 24, 2011 Daily Report for Sunday May 22, 2011

Final grading and erosion controls at SWMU 6;


Posted May 24, 2011 Daily Report for Saturday May 21, 2011

Install culverts beneath 2nd St at B Ave;


Posted May 24, 2011 Daily Report for Friday May 20, 2011

Begin placement of vegetative cover at south half of CAMU;


Posted May 24, 2011 Daily Report for Thursday May 19, 2011

Continue final scraping/excavation of Cell 10 in EQB;


Posted May 21, 2011 Daily Report for Wednesday May 18, 2011

1/2 day due to heavy rain;


Posted May 21, 2011 Daily Report for Tuesday May 17, 2011

Excavate and remove south north 6" OWS pipe beneath SWMU 6 and plug\abandon pipe east of SWRP/EQB;


Posted May 21, 2011 Daily Report for Monday May 16, 2011

Clean south north 6" OWS pipe beneath SWMU 6 and east of SWRP/EQB;


Posted May 18, 2011 Daily Report for Saturday May 14, 2011

Excavated area south of SWMU 6 Area M along east fenceline of Marketing area;


Posted May 17, 2011 Daily Report for Friday May 13, 2011

Completed placement of sand cover on geosynthetics at south half of CAMU;


Posted May 17, 2011 Daily Report for Thursday May 12, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU;


Posted May 17, 2011 Daily Report for Wednesday May 11, 2011

Begin Forms and backfill in AOC 1 for upcoming concrete pour;


Posted May 17, 2011 Daily Report for Tuesday May 10, 2011

Pre-Construction Meeting with Reynolds Inliner; Removed 6" OWS line beneath SWMU 5N;


Posted May 13, 2011 Daily Report for Monday May 9, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU;


Posted May 13, 2011 Daily Report for Saturday May 7, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU;


Posted May 13, 2011 Daily Report for Friday May 6, 2011

Collected post excavation samples from AOC 1, BCP, and SWMU 7 Cell 8;


Posted May 10, 2011 Daily Report for Thursday May 5, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU; Continue demolition/removal of SB44


Posted May 10, 2011 Daily Report for Wednesday May 4, 2011

Heavy rain; Limited Crew onsite to dewater and accept materials


Posted May 10, 2011 Daily Report for Tuesday May 3, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU; Continue demolition/removal of SB44


Posted May 10, 2011 Daily Report for Monday May 2, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU; Begin demolition/removal of SB44


Posted May 10, 2011 Daily Report for Sunday May 1, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU;


Posted May 2, 2011 Daily Report for Saturday April 30, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU; Continued removal of OWS-C East at SE corner of CAMU


Posted May 2, 2011 Daily Report for Friday April 29, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU; Continued removal of OWS-C East at SE corner of CAMU


Posted May 2, 2011 Daily Report for Thursday April 28, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU; Continued removal of OWS-C East at SE corner of CAMU


Posted April 29, 2011 Daily Report for Wednesday April 27, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU; Began removal of remaining sections of OWS-C East at SE corner of CAMU


Posted April 29, 2011 Daily Report for Tuesday April 26, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU;


Posted April 29, 2011 Daily Report for Monday April 25, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU;


Posted April 29, 2011 Daily Report for Saturday April 23, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU;


Posted April 25, 2011 Daily Report for Friday April 22, 2011

Completed BCP excavation and began placement of sand cover on geosynthetics at south third of CAMU


Posted April 25, 2011 Daily Report for Thursday April 21, 2011

Continued BCP excavation and placement of geosynthetics at south third of CAMU


Posted April 21, 2011 Daily Report for Wednesday April 20, 2011

Continued BCP excavation and placement of geosynthetics at south third of CAMU


Posted April 21, 2011 Daily Report for Tuesday April 19, 2011

Continued BCP excavation and placement of geosynthetics at south third of CAMU


Posted April 21, 2011 Daily Report for Monday April 18, 2011

Began BCP excavation; Continued placement of geosynthetics at south third of CAMU


Posted April 21, 2011 Daily Report for Sunday April 17, 2011

Limited work crew onsite; Checked status of liner and dewatered after rains and wind last night


Posted April 21, 2011 Daily Report for Saturday April 16, 2011

Placed SKAPS 330 at south section of CAMU; Prepared work areas for heavy winds and rain forecasted for tonight


Posted April 18, 2011 Daily Report for Friday April 15, 2011

Completed SKAPS 220 geocomposite at southeast section of CAMU and began placement of SKAPS 330; Completed excavation of SWMU 6 asbestos areas and Area M


Posted April 18, 2011 Daily Report for Thursday April 14, 2011

Completed deployment of 60 ml geomembrane at south third of CAMU and began placement of SKAPS 220 geocomposite


Posted April 18, 2011 Daily Report for Wednesday April 13, 2011

Continued to deploy 60 ml geomembrane which progressed from SW corner to west slope of CAMU; Excavated Area M asbestos material under supervision of Western AB personnel


Posted April 18, 2011 Daily Report for Tuesday April 12, 2011

Continued to deploy 60 ml geomembrane at SW corner of CAMU


Posted April 18, 2011 Daily Report for Monday April 11, 2011

Too windy to deploy 60 ml geomembrane; Continued hauling waste from SWMU 7 SWRP and SWMU 6;


Posted April 11, 2011 Daily Report for Sunday April 10, 2011

Limited work crew disced and compacted southwest face of CAMU and dewatered SWMU 7 SWRP;


Posted April 11, 2011 Daily Report for Saturday April 9, 2011

Continued deployment of 60 ml liner to southwest corner of CAMU;


Posted April 11, 2011 Daily Report for Friday April 8, 2011

Continued deployment of 60 ml liner to south section of CAMU; Complete final scraping/excavation of SWRP Cell 3


Posted April 11, 2011 Daily Report for Thursday April 7, 2011

Began deployment of liner at southeast section of CAMU;


Posted April 11, 2011 Daily Report for Wednesday April 6, 2011

Continue final waste grading and compaction at south section of CAMU; Excavated test pits along CAMU East/SWMU 6 fenceline;


Posted April 11, 2011 Daily Report for Tuesday April 5, 2011

No waste hauled to CAMU due to rain; Continued final scraping/excavation of SWRP Cell 3; Grade and compact CAMU surface


Posted April 11, 2011 Daily Report for Monday April 4, 2011

Begin final scraping/excavation of SWRP Cell 3; Finish SWMU 6 Haul Rd Excavation


Posted April 3, 2011 Daily Report for Friday April 1, 2011

Grade and compact CAMU waste; Worked until 3:30; No work tomorrow


Posted April 3, 2011 Daily Report for Thursday March 31, 2011

Intermittent rain all day; Grade and compact CAMU waste


Posted April 3, 2011 Daily Report for Wednesday March 30, 2011

Completed final scraping/excavation of Cell 2 of SWRP and collected bottem sample


Posted April 3, 2011 Daily Report for Tuesday March 29, 2011

Continue CAMU preparation at south end for liner; Continue final scraping/excavation of Cell 2 of SWRP


Posted March 29, 2011 Daily Report for Monday March 28, 2011

Transport Sludge from SWRP Final Excavation and Scraping Activities to Loadout Area and Haul to CAMU; Continue Excavation of Haul Rd in SWMU 6


Posted March 28, 2011 Daily Report for Saturday March 26, 2011

Remove material containing asbestos to roll off containers in SWMU 6


Posted March 28, 2011 Daily Report for Friday March 25, 2011

Continue SWRP Final Excavation and Scraping Activities in Area 3; Prepare South Area of CAMU for Liner


Posted March 28, 2011 Daily Report for Thursday March 24, 2011

Continue SWRP Final Excavation and Scraping Activities in Areas 2 and 3; Prepare South Area of CAMU for Liner


Posted March 25, 2011 Daily Report for Wednesday March 23, 2011

Continue SWRP Final Excavation and Scraping Activities in Areas 2 and 3; Prepare South Area of CAMU for Liner


Posted March 25, 2011 Daily Report for Tuesday March 22, 2011

Continue SWRP Final Excavation and Scraping Activities; Prepare South Area of CAMU for Liner


Posted March 22, 2011 Daily Report for Monday March 21, 2011

Completed final scraping in Area 1.


Posted March 22, 2011 Daily Report for Sunday March 20, 2011

Continue surface preparation in CAMU. Move sludge from EQB to load out area in SWRP.


Posted March 22, 2011 Daily Report for Saturday March 19, 2011

Continue excavation of Area 1.


Posted March 21, 2011 Daily Report for Friday March 18, 2011

Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7; Begin excavating and scraping Area 1 of SWRP to grade


Posted March 21, 2011 Daily Report for Thursday March 17, 2011

Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7


Posted March 18, 2011 Daily Report for Wednesday March 16, 2011

Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7


Posted March 18, 2011 Daily Report for Tuesday March 15, 2011

Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7


Posted March 16, 2011 Daily Report for Monday March 14, 2011

Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7


Posted March 15, 2011 Daily Report for Sunday March 13, 2011

Limited work crew on-site to add/blend LKD in SWRP and EQB


Posted March 15, 2011 Daily Report for Saturday March 12, 2011

Resume hauling activities from SWMU 6 and SWMU 7


Posted March 15, 2011 Daily Report for Friday March 11, 2011

Dewater work areas after heavy rain.


Posted March 14, 2011 Daily Report for Thursday March 10, 2011

Repair site following rain. Excavate haul road in SWMU 6 near marketing terminal entrance.


Posted March 10, 2011 Daily Report for Wednesday March 9, 2011

Excavation in SWMU 6 at North Perimeter (outside former fenceline).


Posted March 10, 2011 Daily Report for Tuesday March 8, 2011

Excavation in SWMU 6 at North Perimeter. Encountered deeper area of waste.


Posted March 9, 2011 Daily Report for Monday March 7, 2011

Continue CAMU Waste Management and Excavation in SWMU 6 at North Perimeter (outside former fenceline)


Posted March 7, 2011 Daily Report for Friday March 4, 2011

Continued excavation in SWMU 6 and SWMU 7; Envirocon to take day off tomorrow (Saturday March 5, 2011)


Posted March 7, 2011 Daily Report for Thursday March 3, 2011

Continued excavation in SWMU 6 and SWMU 7


Posted March 3, 2011 Daily Report for Wednesday March 2, 2011

Continued excavation in SWMU 6, SWMU 7, and AOC 1


Posted March 3, 2011 Daily Report for Tuesday March 1, 2011

Excavation in AOC 1 only due to wet conditions


Posted March 3, 2011 Daily Report for Monday February 28, 2011

Continue excavation of SWMU 6 and AOC 1


Posted March 1, 2011 Daily Report for Saturday February 26, 2011

Began potholing and excavation of AOC 1


Posted March 1, 2011 Daily Report for Friday February 25, 2011

No excavation and/or hauling activities conducted; 1/2 day due to rain


Posted March 1, 2011 Daily Report for Thursday February 24, 2011

Continued SWMU 6 excavation and began east perimeter ditch of CAMU;


Posted March 1, 2011 Daily Report for Wednesday February 23, 2011

Continued SWMU 6 excavation and south perimeter ditch of CAMU;


Posted March 1, 2011 Daily Report for Tuesday February 22, 2011

Continued SWMU 6 excavation and south perimeter ditch of CAMU;


Posted March 1, 2011 Daily Report for Monday February 21, 2011

Continued SWMU 6 excavation and began excavating CAMU south perimeter ditch;


Posted February 23, 2011 Daily Report for Saturday February 19, 2011

Finish SWMU 10 excavtion;


Posted February 22, 2011 Daily Report for Friday February 18, 2011

Continue Waste placement from SWMU 6 and SWMU 10;


Posted February 22, 2011 Daily Report for Thursday February 17, 2011

Continue Waste placement from SWMU 6 and SWMU 10;


Posted February 22, 2011 Daily Report for Wednesday February 16, 2011

Continue Waste placement from SWMU 6 and SWMU 10;


Posted February 22, 2011 Daily Report for Tuesday February 15, 2011

Continue Waste placement from SWMU 6 and SWMU 10;


Posted February 16, 2011 Daily Report for Monday February 14, 2011

Continue Waste placement from SWMU 6 and SWMU 10;


Posted February 16, 2011 Daily Report for Saturday February 12, 2011

Continue Waste placement from SWMU 6; Resume excavation activities at SWMU 10


Posted February 16, 2011 Daily Report for Friday February 11, 2011

Continue Waste placement from SWMU 6; Begin installation of new fence at SWMU 6


Posted February 15, 2011 Daily Report for Thursday February 10, 2011

Limited day due to snow; 1/2 day of dewatering and decon activities;


Posted February 15, 2011 Daily Report for Wednesday February 9, 2011

Excavate and haul from SWMU 6; Begin addition of LKD to west section of EQB;


Posted February 15, 2011 Daily Report for Tuesday February 8, 2011

Excavate and haul from SWMU 6; Constructed access ramp from SWRP to CAMU;


Posted February 15, 2011 Daily Report for Monday February 7, 2011

Excavate and haul from SWMU 6 and SWMU 10 (severed power cable in SWMU 10; work ceased); Potholed outside SWMU 6 fenceline between BCP and Area M;


Posted February 9, 2011 Daily Report for Saturday February 5, 2011

No waste hauled to CAMU; 1/2 work day due to heavy rain;


Posted February 9, 2011 Daily Report for Friday February 4, 2011

Continued excavation and hauling out of SWMU 6


Posted February 8, 2011 Daily Report for Thursday February 3, 2011

Conducted potholing activities outside of fenceline at SWMU 6


Posted February 8, 2011 Daily Report for Wednesday February 2, 2011

Limited work due to rain; Dewatered work areas


Posted February 8, 2011 Daily Report for Tuesday February 1, 2011

Begin demolition of EQB concrete pump structure; Continue backfilling FBP and excavation at SWMU 6


Posted February 8, 2011 Daily Report for Monday January 31, 2011

Continue to backfill FBP; Load and haul concrete debris from SWMU 10 to CAMU;


Posted February 2, 2011 Daily Report for Saturday January 29, 2011

Finalize FBP excavation and begin backfill activities;


Posted February 2, 2011 Daily Report for Friday January 28, 2011

Continue excavation of FBP and collect post excavation samples;


Posted February 2, 2011 Daily Report for Thursday January 27, 2011

Continue excavation of FBP; Begin demolition of concrete pad at SWMU 10;


Posted February 2, 2011 Daily Report for Wednesday January 26, 2011

Rain Day; Dewater Work Areas


Posted January 26, 2011 Daily Report for Tuesday January 25, 2011

Continue adding/mixing LKD into SWRP; Continue excavation of FBP area


Posted January 26, 2011 Daily Report for Monday January 24, 2011

Continue adding/mixing LKD into SWRP; Continue excavation of FBP area


Posted January 25, 2011 Daily Report for Saturday January 22, 2011

Continue adding/mixing LKD into SWRP; Begin excavation of FBP area


Posted January 25, 2011 Daily Report for Friday January 21, 2011

Continue adding/mixing LKD into SWRP; Continue demo of FBP berms and pump structure


Posted January 25, 2011 Daily Report for Thursday January 20, 2011

Continue adding/mixing LKD into SWRP; Continue demo of FBP berms and pump platform


Posted January 21, 2011 Daily Report for Wednesday January 19, 2011

Begin closure of FBP mixing area by pushing in berms and demolition of pump platform


Posted January 21, 2011 Daily Report for Tuesday January 18, 2011

Dewater work areas and repair haul roads after rains last evening


Posted January 21, 2011 Daily Report for Monday January 17, 2011

Backfill SWMU 9; Continue excavation and hauling activities in SWMU 6; Prepare for forecasted rain


Posted January 21, 2011 Daily Report for Saturday January 15, 2011

Backfill SWMU 9; Continue excavation and hauling activities in SWMU 6;


Posted January 17, 2011 Daily Report for Friday January 14, 2011

Backfill SWMU 9; Continue excavation and hauling activities in SWMU 6;


Posted January 17, 2011 Daily Report for Thursday January 13, 2011

Backfill SWMU 9; Continue excavation and hauling activities in SWMU 6;


Posted January 17, 2011 Daily Report for Wednesday January 12, 2011

Backfill SWMU 9; Excavation and Hauling activities in SWMU 6; Begin addition of LKD directly to SWRP


Posted January 14, 2011 Daily Report for Tuesday January 11, 2011

Backfill SWMU 9; Prepare for excavation activities in SWMU 6


Posted January 14, 2011 Daily Report for Monday January 10, 2011

Backfill SWMU 9; Dewater and clear trees from SWMU 6


Posted January 11, 2011 Daily Report for Saturday January 8, 2011

Backfill SWMU 9; Dewater Area A and clear trees from SWMU 6


Posted January 11, 2011 Daily Report for Friday January 7, 2011

Complete excavation activities at SWMU 9 and begin backfilling


Posted January 10, 2011 Daily Report for Thursday January 6, 2011

Continue waste placement and management at CAMU from SWMU 7 and SWMU 9; Evanco completed OWS Cleaning and Inspection Scope of Work


Posted January 7, 2011 Daily Report for Wednesday January 5, 2011

Continue waste placement and management at CAMU from SWMU 7 and SWMU 9;


Posted January 7, 2011 Daily Report for Tuesday January 4, 2011

Continue waste placement and management at CAMU from SWMU 7 and SWMU 9;


Posted January 7, 2011 Daily Report for Monday January 3, 2011

Return from holiday downtime; Dewater work areas and disc/grade CAMU


Posted January 5, 2011 Daily Report for Wednesday December 22, 2010

Clean up and prepare site for holiday downtime; Will resume work January 3, 2011


Posted December 23, 2010 Daily Report for Tuesday December 21, 2010

Continue Waste Placement in CAMU from SWMU 7 and 9; Evanco completed cleaning and inspection of OWS-1A (ASB58 to SB60)


Posted December 23, 2010 Daily Report for Monday December 20, 2010

Continue Waste Placement in CAMU from SWMU 7 and 9; Evanco completed cleaning and inspection of OWS Sump and OWS Sump to SB42


Posted December 21, 2010 Daily Report for Sunday December 19, 2010

Limited Envirocon crew conducted pumping/solidification at SWMU 7; Evanco continued cleaning from OWS Sump to SB42


Posted December 21, 2010 Daily Report for Saturday December 18, 2010

Continue Waste Placement in CAMU from SWMU 7 and 9; Evanco continued cleaning from OWS Sump to SB42


Posted December 21, 2010 Daily Report for Friday December 17, 2010

Snow and ice clean up; Hauled waste from FBP to CAMU; Evanco conducted initial cleaning of OWS-1A from SB60


Posted December 21, 2010 Daily Report for Thursday December 16, 2010

Continue Waste Placement in CAMU from SWMU 7 and 9; Early shutdown due to snow;


Posted December 18, 2010 Daily Report for Wednesday December 15, 2010

Continue Waste Placement in CAMU from SWMU 7 and 9; Evanco continued cleaning and inspection at OWS Sump, SB41, and SB42


Posted December 18, 2010 Daily Report for Tuesday December 14, 2010

Continue Waste Placement in CAMU from SWMU 7 and 9; Evanco continued cleaning and inspection at OWS Sump, SB41, and SB42


Posted December 18, 2010 Daily Report for Monday December 13, 2010

Manage Waste in CAMU and Dewater SWMUs after rain event; Evanco continued cleaning OWS Sump


Posted December 13, 2010 Daily Report for Saturday December 11, 2010

Continue Excavation of SWMU 9; Limited Evanco crew began laydown/set up of by pass line from SB58 to SB59


Posted December 13, 2010 Daily Report for Friday December 10, 2010

Continue Excavation of SWMU 9; Evanco began cleaning of OWS Sump to SB41


Posted December 13, 2010 Daily Report for Thursday December 9, 2010

Continue Excavation of SWMU 9;


Posted December 10, 2010 Daily Report for Wednesday December 8, 2010

Continue Excavation of SWMU 9;


Posted December 10, 2010 Daily Report for Tuesday December 7, 2010

Continue Excavation of SWMU 9;


Posted December 10, 2010 Daily Report for Monday December 6, 2010

Continue Excavation of SWMU 9;


Posted December 7, 2010 Daily Report for Saturday December 4, 2010

Continue Excavation of SWMU 9;


Posted December 7, 2010 Daily Report for Friday December 3, 2010

Continue Excavation of SWMU 9; Evanco completed final CCTV of SB37 to SB40 and SB35 to SB37


Posted December 6, 2010 Daily Report for Thursday December 2, 2010

Continue Excavation of SWMU 9; Evanco continued cleaning SB37 to SB40


Posted December 3, 2010 Daily Report for Wednesday December 1, 2010

Limited Work day due to Weather;


Posted December 3, 2010 Daily Report for Tuesday November 30, 2010

Began SWMU 9 Excavation;


Posted December 2, 2010 Daily Report for Monday November 29, 2010

Prepared for SWMU 9 Excavation;


Posted November 29, 2010 Daily Report for Wednesday November 24, 2010

Cleaned and secured work areas for Thanksgiving Holiday;


Posted November 29, 2010 Daily Report for Tuesday November 23, 2010

Continued waste management in CAMU West; Evanco continued cleaning from SB35 to SB37;


Posted November 29, 2010 Daily Report for Monday November 22, 2010

Continued waste placement/management in CAMU West from SWMU 7 and SWMU 6 Area F overexcavation; Evanco began cleaning from SB35 to SB37;


Posted November 29, 2010 Daily Report for Saturday November 20, 2010

Cleaned east/west 6" OWS line in SWMU 5N;


Posted November 29, 2010 Daily Report for Friday November 19, 2010

Continue waste placement/management in CAMU West from SWMU 7 and SWMU 6 Area C Overexcavation; Evanco completed cleaning and CCTV Inspection from SB10 to SB35;


Posted November 19 2010 Daily Report for Thursday November 18, 2010

Continue waste placement/management in CAMU West from SWMU 7 and SWMU 6 Area D; Evanco continued cleaning from SB10 to SB35


Posted November 19 2010 Daily Report for Wednesday November 17, 2010

Continue waste placement/management in CAMU West from SWMU 7 and SWMU 6 Area D; Evanco continued cleaning from SB10 to SB35


Posted November 19 2010 Daily Report for Tuesday November 16, 2010

Continue waste placement/management in CAMU West from SWMU 7 and SWMU 6 Areas K and L; Evanco continued cleaning from SB10 to SB35


Posted November 16 2010 Daily Report for Monday November 15, 2010

Continue waste placement/management in CAMU West from SWMU 6 Areas K and L; Evanco began cleaning from SB10 to SB35


Posted November 16 2010 Daily Report for Saturday November 13, 2010

Continue waste placement/management in CAMU West from SWMU 7; Evanco not onsite


Posted November 16 2010 Daily Report for Friday November 12, 2010

Continue waste placement/management in CAMU West from SWMU 6 Areas I and J; Evanco completed cleaning and final CCTV inspectin from SB7 to SB10


Posted November 15 2010 Daily Report for Thursday November 11, 2010

Continue waste placement/management in CAMU West from SWMU 6 and SWMU 7; Evanco cleaning SB7 to SB10


Posted November 15 2010 Daily Report for Wednesday November 10, 2010

Continue waste placement/management in CAMU West from SWMU 6 and SWMU 7; Evanco completed final CCTV from SB6 to SB7


Posted November 11 2010 Daily Report for Tuesday November 9, 2010

Continue waste placement/management in CAMU West from SWMU 6, SWMU 5N, and SWMU 7; Evanco finished cleaning from SB6 to SB7


Posted November 11 2010 Daily Report for Monday November 8, 2010

Continue waste placement/management in CAMU West from SWMU 6, SWMU 5N, and SWMU 7; Evanco continued cleaning from SB6 to SB7


Posted November 9, 2010 Daily Report for Saturday November 6, 2010

Limited Envirocon crew onsite for equipment maintenance and accepting LKD deliveries; Evanco not onsite


Posted November 9, 2010 Daily Report for Friday November 5, 2010

Continued dewatering of excavation areas after rain; Evanco continued to clean SB6 to SB7


Posted November 8, 2010 Daily Report for Thursday November 4, 2010

Envirocon dewatered excavation areas after rain; Evanco continued to clean SB6 to SB7


Posted November 5, 2010 Daily Report for Wednesday November 3, 2010

Removed remainder of 24" Spillway in south wall of SWMU 5N excavation (leftover from Phase I CMI activities; Evanco continued to clean SB6 to SB7


Posted November 4, 2010 Daily Report for Tuesday November 2, 2010

Continued Waste Placement Activities from SWMU 6 and SWMU 7; Removed 6" OWS line from SWMU 5N; Evanco continued to clean SB6 to SB7


Posted November 4, 2010 Daily Report for Monday November 1, 2010

Continued Waste Placement Activities from SWMU 6 and SWMU 7; Evanco continued to clean SB6 to SB7


Posted November 3, 2010 Daily Report for Saturday October 30, 2010

Limited work; Continued trial testing modified LKD delivery method;


Posted November 3, 2010 Daily Report for Friday October 29, 2010

Continued dewatering activities; Decon sheetpile; Trial tested modified LKD delivery method; Evanco continued to clean SB6 to SB7;


Posted November 3, 2010 Daily Report for Thursday October 28, 2010

Limited work due to heavy rain; Dewatering of SWMU 6 and SWMU 5N excavations;


Posted October 30, 2010 Daily Report for Wednesday October 27, 2010

Excavated 24" spillway from SWMU 5N;


Posted October 29, 2010 Daily Report for Tuesday October 26, 2010

Excavated 2-6" and 2-16" pipes from SWMU 5N;


Posted October 29, 2010 Daily Report for Monday October 25, 2010

Began excavation of Areas G and F in SWMU 6; Collected verification samples from Areas A, B, C in SWMU 6;


Posted October 25, 2010 Daily Report for Saturday October 23, 2010

Removed Transite pipe from SWMU 5N; Began excavation Area A and M in SWMU 6;


Posted October 25, 2010 Daily Report for Friday October 22, 2010

Completing excavation activities in SWMU 5N and continued excavation of Area C and B in SWMU 6; Evanco delivered 16yds material to FBP N mixing cell;


Posted October 25, 2010 Daily Report for Thursday October 21, 2010

Begin Excavation of Area C and B in SWMU 6;


Posted October 25, 2010 Daily Report for Wednesday October 20, 2010

Continued excavation in SWMU 5N;


Posted October 22, 2010 Daily Report for Tuesday October 19, 2010

Excavated CW312 area in SWMU 5N


Posted October 22, 2010 Daily Report for Monday October 18, 2010

Continued Waste Placement activities in CAMU W (from SWMU 5N and SWMU 7)


Posted October 20, 2010 Daily Report for Saturday October 16, 2010

Conducted CAMU West Waste Management activities by discing, rolling, and grading material from SWMU 5N and SWMU 7


Posted October 20, 2010 Daily Report for Friday October 15, 2010

Continued Waste Placement Activities in CAMU W and Review of Pilot Study Report; Continued OWS CIR Activities


Posted October 16, 2010 Daily Report for Thursday October 14, 2010

Continued Waste Placement Activities in CAMU W and Review of Pilot Study Report; Continued OWS CIR Activities


Posted October 16, 2010 Daily Report for Wednesday October 13, 2010

Continued Waste Placement Activities in CAMU W and Preparation of Pilot Study Report; Continued OWS CIR Activities


Posted October 15, 2010 Daily Report for Tuesday October 12, 2010

Continued Waste Placement Activities in CAMU W and Preparation of Pilot Study Report; Continued OWS CIR Activities


Posted October 15, 2010 Daily Report for Monday October 11, 2010

Hauled and Placed N Mixing Cell of FBP into CAMU Test Pads as Part of Final Phase 3 Pilot Study; Continued OWS CIR Activities


Posted October 12, 2010 Daily Report for Saturday October 9, 2010

Filled N Mixing Cell of FBP as Part of Final Phase 3 Pilot Study; No OWS CIR Work Conducted


Posted October 12, 2010 Daily Report for Friday October 8, 2010

Envirocon Tested Methods for Adding LKD Reagent with Minimal Dust; Resume Inspection from SB1 to Tank 10 and Begin Cleaning from SB1 to SB2;


Posted October 9, 2010 Daily Report for Thursday October 7, 2010

Continue Dewatering Phase II CMI Work Areas; Continue OWS CIR from SB1 to Tank 900


October 8, 2010 Daily Report for Wednesday October 6, 2010

Continue Dewatering Phase II CMI Work Areas; Begin OWS CIR from SB1 to Tank 10


October 8, 2010 Daily Report for Tuesday October 5, 2010

Continue Dewatering Phase II CMI Work Areas


October 8, 2010 Daily Report for Monday October 4, 2010

Continue Dewatering Phase II CMI Work Areas


October 4, 2010 Daily Report for Sunday October 3, 2010

Begin 24 Hour Dewatering of Work Areas


October 4, 2010 Daily Report for Saturday October 2, 2010

Set Up Pumps and Prepare to Dewater Work Areas


October 4, 2010 Daily Report for Friday October 1, 2010

Inspection of Storm Water E&S Controls


October 4, 2010 Daily Report for Thursday September 30, 2010

Phase II CMI Activities Limited Due to Heavy Rain


October 1, 2010 Daily Report for Wednesday September 29, 2010

Prepare for Forecasted Tropical Storm Weather Front


October 1, 2010 Daily Report for Tuesday September 28, 2010

Evanco Continues Installation of Bypass Manifold; Mix Test Batches of Sludge as Part of Phase 3 Pilot Study


September 29, 2010 Daily Report for Monday September 27, 2010

Continue Revised Phase 3 of Pilot Study; Evanco Begins Installation of Bypass Manifold.


September 28, 2010 Daily Report for Saturday September 25, 2010

Continue SWMU 5N Excavation; Continue Revised Phase 3 of Pilot Study.


September 28, 2010 Daily Report for Friday September 24, 2010

Continue SWMU 5N Excavation; Resume OWS-C East Excavation; Begin Revised Phase 3 of Pilot Study.


September 24, 2010 10 09 23 Daily Report

Continue SWMU 5N Excavation.


September 24, 2010 10 09 22 Daily Report

Beginning of SWMU 5 N Excavation.


September 24, 2010 10 09 21 Daily Report

Continue Excavation and Removal OWS-C East.


September 22, 2010 10 09 20 Daily Report

Continue Excavation and Removal OWS-C East.


September 21, 2010 10 09 17 Daily Report

Continue Excavation and Removal OWS-C East.


September 21, 2010 10 09 16 Daily Report

Begin Excavation and Removal OWS-C East.


September 17, 2010 10 09 15 Daily Report

Complete Cleaning of OWS-C East; Continued Excavation of SWMU 2.


September 17, 2010 10 09 14 Daily Report

Partial Sampling Conducted in SWMU 2; Continued Cleaning of OWS-C East.


September 17, 2010 10 09 13 Daily Report

Continued Excavation of SWMU 2; Cleaning of OWS-C East.


September 13, 2010 10 09 11 Daily Report

Day 22 Pilot Study.


September 13, 2010 10 09 10 Daily Report

Day 21 Pilot Study.


September 13, 2010 10 09 09 Daily Report

Day 20 Pilot Study.


September 13, 2010 10 09 08 Daily Report

Day 19 of Pilot Study.


September 10, 2010 10 09 07 Daily Report

Day 18 Initiate Dredge Phase III of Pilot Study.


September 10, 2010 10 09 03 Daily Report

Day 17 of Pilot Study.


September 7, 2010 10 09 02 Daily Report

Day 16 Initiate Dredge Phase III of Pilot Study.


September 7, 2010 10 09 01 Daily Report

Day 15 of Pilot Study.


September 2, 2010 10 08 31 Daily Report

Day 14 of Pilot Study.


September 2, 2010 10 08 30 Daily Report

Day 13 of Pilot Study.


August 30, 2010 10 08 27 Daily Report

Day 12 of Pilot Study.


August 27, 2010 10 08 26 Daily Report

Day 11 of Pilot Study.


August 26, 2010 10 08 25 Daily Report

Day Ten of Pilot Study.


August 26, 2010 10 08 24 Daily Report

Day Nine of Pilot Study.


August 25, 2010 10 08 23 Daily Report

Day Eight of Pilot Study.


August 23, 2010 10 08 21 Daily Report

Day Seven of Pilot Study.


August 23, 2010 10 08 20 Daily Report

Day Six of Pilot Study.


August 20, 2010 10 08 19 Daily Report

Day Five of Stage 1 Pilot Study.


August 20, 2010 10 08 18 Daily Report

Day Four of Stage 1 Pilot Study.


August 20, 2010 10 08 17 Daily Report

Day Three of Stage 1 Pilot Study.


August 18, 2010 10 08 16 Daily Report

Day Two of Stage 1 Pilot Study.


August 17, 2010 10 08 14 Daily Report

Day One of Stage 1 Pilot Study.


August 16, 2010 10 08 13 Daily Report

Prepare for Stage 1 of Pilot Study.


August 16, 2010 10 08 12 Daily Report

Topo survey of SWRP TSWRB 40ml liner delivered to site.


August 13, 2010 10 08 11 Daily Report

Place Dredge into SWRP Continue CAMU Berms and Access Egress Ramps.


August 13, 2010 10 08 10 Daily Report

Set Up and Calibrate Survey Equipment for Dredge.


August 10, 2010 10 08 09 Daily Report

Dredge Mobilized to Site RFIs and Transmittals Attached.


August 08, 2010 10 08 07 Daily Report

Begin welding HDPE for upcoming dredge operations.


August 08, 2010 10 08 06 Daily Report

Continued preparation CAMU berms and TSWRB.


August 08, 2010 10 08 05 Daily Report

Complete final SWMU 8 hot spot excavation.


August 05, 2010 10 08 04 Daily Report

Continued Excavation SWMU 8.


August 05, 2010 10 08 03 Daily Report

Begin SWMU 8 Excavation and N Berm Construction.


August 04, 2010 10 08 02 Daily Report

Continued Excavation TSWRB.


August 02, 2010 10 07 31 Daily Report

Continued Excavation TSWRB.


August 02, 2010 10 07 30 Daily Report

Backfill C6 Excavation.


August 02, 2010 10 07 29 Daily Report

Complete C6 NAPL Excavation.


July 29, 2010 10 07 28 Daily Report

Began C-6 NAPL Area excavation.


July 29, 2010 10 07 27 Daily Report

Began construction of TSWRB.


July 27, 2010 10 07 26 Daily Report

Surveyed boundaries for SWMU 9, 10, 8.


July 26, 2010 10 07 23 Daily Report

Began construction of South berm of Temporary Stormwater Retention Basin.


July 23, 2010 10 07 22 Daily Report

Chipping in SWMU 2 begins.


July 22, 2010 10 07 21 Daily Report

Began preparing CAMU West test pad area.


July 22, 2010 10 07 20 Daily Report

Proof rolling in CAMU West. Clearing SWMU 2 continues.


July 20, 2010 10 07 19 Daily Report

Clearing CAMU West. Clearing SWMU 2 begins.


July 20, 2010 10 07 17 Daily Report

Clearing CAMU West.


July 19, 2010 10 07 16 Daily Report

Surveying CAMU West.


July 16, 2010 10 07 15 Daily Report

Clearing and Surveying CAMU West.


July 16, 2010 10 07 14 Daily Report

Continue Clearing SWMU 5 North and SWMU 6.


July 13, 2010 10 07 13 Daily Report

Access Road and locate SWMU 6 excavation areas.


July 12, 2010 10 07 12 Daily Report

SWMU 5 and SWMU 6 mowing.


July 11, 2010 10 07 11 Daily Report

Background PAMP monitoring.


July 10, 2010 10 07 10 Daily Report

Background PAMP monitoring.


July 9, 2010 10 07 09 Daily Report

Clearing and surveying of SWMU 6. Background PAMP monitoring.


July 8, 2010 10 07 08 Daily Report

Clearing and surveying of SWMU 6. Background PAMP monitoring.


July 7, 2010 10 07 07 Daily Report

Surveyors begin work.


July 6, 2010 10 07 06 Daily Report

Envirocon work crew begin site orientation.


June 18, 2010 10 06 09 Daily Report

PAMP monitoring stations were installed.