Continue grading and seeding/erosion controls in SWMU 5N and SWMU 7
Continue grading and seeding/erosion controls in SWMU 5N and SWMU 7
Continue grading and seeding/erosion controls in SWMU 5N and SWMU 7
Continue grading and seeding/erosion controls in SWMU 5N and SWMU 7
Placement of erosion controls in SWMU 6; Continue grading SWMU 6 and SWMU 7;
Continue placement of erosion controls in CAMU;
Continue seeding/erosion controls in CAMU; Final grading activities in SWMU 6 and SWMU 7; Reynolds completed cleaning and rehabilitation of SB7
Continue seeding/erosion controls in CAMU; Final grading activities in SWMU 6 and SWMU 7;
Final grading activities in SWMU 6 and SWMU 7;
Opal, Western, and Envirocon prepare punch list for final walk through activities;
Continue seeding/ erosion/sediment control of CAMU surface and ditches;
Continue seeding and erosion/sediment control mats at South End of CAMU;
Continue seeding and erosion/sediment control mats at South End of CAMU;
Complete installation of culvert from EQB to Settling Basin;
Begin installation of culvert from EQB to Settling Basin; Begin installation of erosion control mats in CAMU ditches and seeding preparation
Continue installation of culverts at SW corner of CAMU;
Began Installation of culverts at SW corner of CAMU;
Continued placement of topsoil on north half of CAMU;
Continued placement of topsoil on north half of CAMU;
Continued placement of topsoil on north half of CAMU; Reynolds SB Rehab crew completed cleaning/rehab of SB35 and departed site until 8/8/11;
Continued placement of topsoil on north half of CAMU; Reynolds SB Rehab crew completed cleaning/rehab of SB42;
Began placement of topsoil on north half of CAMU; Reynolds SB Rehab crew completed cleaning/rehab of SB40;
Completed placement of VA#10 at north half of CAMU; Reynolds SB Rehab crew temporarily ceased rehab of SB7 and completed cleaning/rehab of SB59;
Continued placement and grading of VA#10 at north half of CAMU; Reynolds Sewer Box Rehab crew continued rehab of SB7;
Continued placement and grading of VA#10 at north half of CAMU; Reynolds Sewer Box Rehab crew completed rehab of SB60;
Continued placement and grading of VA#10 at north half of CAMU; Reynolds Sewer Box Rehab crew began cleaning SB60;
Continued placement and grading of VA#10 at north half of CAMU; Reynolds Sewer Box Rehab crew cleaned and rehabilitated ASB58 and SB58;
Continued placement and grading of VA#10 at north half of CAMU; Reynolds installed CIPP from SB59 to SB60;
Continued placement and grading of VA#10 at north half of CAMU; Reynolds installed CIPP from ASB58 through SB58 to SB59;
Completed permanent stormwater culverts at NW corner of CAMU beneath Ave A; Reynolds cleaned and conducted Pre-CCTV from ASB58 to SB60;
AEGL completed CAP system with final installation of geocomposite; Reynolds lined SB5A to SB5B
Begin installation of permanent stormwater culverts at NW corner of CAMU beneath Ave A;
Installed final 60 ml geomembrane panels at north edge of CAMU; Reynolds Inliner lined from Tk10 to SB1 and completed SB rehabilitation at Tk613 and SB38;
Resumed re-grading/drying material at north edge of CAMU; Reynolds Inliner lined from Tk613 to SB38 and finished rehab activities at SB6;
Continued to dewater work areas; Reynolds Inliner back onsite and cleaned/inpected Tk613 to SB38 for lining tomorrow;
Continued to dewater work areas;
Rain greater than 4" over last 24 hours; Dewatered work areas;
Installed 15,000 sqf of TN220 composite at north end of CAMU; CAMU 97% lined; Heavy rains forecasted;
Installed 27,852 sqf of HDPE at north end of CAMU;
Heavy Rain; Continue to dewater, re-grade, and dry remaining waste surface for installation of remaining CAP;
Prepare waste surface (re-grade/dry) for installation of remaining CAP on former TSWRB (pending weather);
Rain; Limited Envirocon crew onsite to maintain dewatering pumps;
Install geomembrane panels and geocomposite on former TSWRB to the extent conditions would allow;
Install geomembrane panels on former TSWRB to the extent conditions would allow;
Prepare waste surface (re-grade/dry) for installation of CAP on former TSWRB;
Installation of CAP at former TSWRB delayed due to wet conditions;
Installation of CAP at former TSWRB delayed due to wet conditions;
Installation of CAP at former TSWRB delayed due to heavy rain yesterday;
Installation of CAP at former TSWRB delayed due to heavy rain in early AM;
Resumed installation of geomembrane cap at North end of CAMU; Reynolds Inliner installed CIPP from SB2 to SB1;
Completed TSWRB closure and final grading at North end of CAMU; Reynolds Inliner conducted Post-CCTV from SB38 to SB40;
Continue TSWRB closure; Reynolds Inliner installed CIPP from SB38 to SB40;
Continue TSWRB closure; Reynolds Inliner installed CIPP from Tk 900 to SB1 and from SB5A to SB5;
Continue TSWRB closure; Reynolds Inliner installed CIPP from SB14 to SB5B;
Continue installation of geosynthetic cap and TSWRB closure; Reynolds Inliner installed CIPP from SB18 to SB14;
Continue installation of geosynthetic cap and TSWRB closure; Reynolds Inliner back onsite and continued OWS CIR activities
Limited crew grading waste and maintaining ditch pumps
Continue cap installation and closure of TSWRB
Continue cap installation; Begin closure of TSWRB
Continue cap installation;
Continue cap installation; Continue OWS point repairs
Continue cap installation; Begin OWS point repairs
Continue installation of geomembrane cap system; Reynolds offsite until 6/20/11
Complete excavation activities at SWMU 7; Reynolds offsite until 6/20/11
Complete excavation activities at SWMU 7; Reynolds offsite until 6/20/11
Begin installation of geomembrane cap on North half of CAMU; Reynolds demobilized until 6/20/11
Continue excavation of area between SWRP and FBP; Reynolds installed CIPP from SB42 to Money Pit
Continue excavation of area between SWRP and FBP; Reynolds prepared to install CIPP from SB42 to Money Pit
Completing SWRP Areas 5/12 and begin area between SWRP and FBP; Reynolds installed CIPP from SB40 to Money Pit
Continued excavation of SWRP Area 5; Reynolds installed CIPP from SB40 to SB37
Continued excavation of SWRP Area 5;
Continued excavation of Area 12 and 5; Reynolds installed CIPP from SB35 to SB37;
Continued excavation of Area 12; Prepared to install CIPP from SB35 to SB37;
Continued excavation of Area 12; Reynolds installed 503' of 48" CIPP from SB10 to SB35;
Maintained ditch pumps; Reynolds Inliner cut laterals for CIPP from SB7 to SB10;
Maintained ditch pumps; Reynolds Inliner installed CIPP from SB7 to SB10;
Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed final CCTV and prepared for 48" CIPP installation from SB10 to SB7;
Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed 36" CIPP installation from SB6 to SB7;
Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed final CCTV and prepared for 36" CIPP installation from SB6 to SB7;
Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed 21" CIPP installation from SB6 to SB3;
Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed final CCTV and prepared for 21" CIPP installation from SB6 to SB3;
Final grading and erosion controls at SWMU 6;
Install culverts beneath 2nd St at B Ave;
Begin placement of vegetative cover at south half of CAMU;
Continue final scraping/excavation of Cell 10 in EQB;
1/2 day due to heavy rain;
Excavate and remove south north 6" OWS pipe beneath SWMU 6 and plug\abandon pipe east of SWRP/EQB;
Clean south north 6" OWS pipe beneath SWMU 6 and east of SWRP/EQB;
Excavated area south of SWMU 6 Area M along east fenceline of Marketing area;
Completed placement of sand cover on geosynthetics at south half of CAMU;
Continued placement of sand cover on geosynthetics at south half of CAMU;
Begin Forms and backfill in AOC 1 for upcoming concrete pour;
Pre-Construction Meeting with Reynolds Inliner; Removed 6" OWS line beneath SWMU 5N;
Continued placement of sand cover on geosynthetics at south half of CAMU;
Continued placement of sand cover on geosynthetics at south half of CAMU;
Collected post excavation samples from AOC 1, BCP, and SWMU 7 Cell 8;
Continued placement of sand cover on geosynthetics at south half of CAMU; Continue demolition/removal of SB44
Heavy rain; Limited Crew onsite to dewater and accept materials
Continued placement of sand cover on geosynthetics at south half of CAMU; Continue demolition/removal of SB44
Continued placement of sand cover on geosynthetics at south half of CAMU; Begin demolition/removal of SB44
Continued placement of sand cover on geosynthetics at south half of CAMU;
Continued placement of sand cover on geosynthetics at south half of CAMU; Continued removal of OWS-C East at SE corner of CAMU
Continued placement of sand cover on geosynthetics at south half of CAMU; Continued removal of OWS-C East at SE corner of CAMU
Continued placement of sand cover on geosynthetics at south half of CAMU; Continued removal of OWS-C East at SE corner of CAMU
Continued placement of sand cover on geosynthetics at south half of CAMU; Began removal of remaining sections of OWS-C East at SE corner of CAMU
Continued placement of sand cover on geosynthetics at south half of CAMU;
Continued placement of sand cover on geosynthetics at south half of CAMU;
Continued placement of sand cover on geosynthetics at south half of CAMU;
Completed BCP excavation and began placement of sand cover on geosynthetics at south third of CAMU
Continued BCP excavation and placement of geosynthetics at south third of CAMU
Continued BCP excavation and placement of geosynthetics at south third of CAMU
Continued BCP excavation and placement of geosynthetics at south third of CAMU
Began BCP excavation; Continued placement of geosynthetics at south third of CAMU
Limited work crew onsite; Checked status of liner and dewatered after rains and wind last night
Placed SKAPS 330 at south section of CAMU; Prepared work areas for heavy winds and rain forecasted for tonight
Completed SKAPS 220 geocomposite at southeast section of CAMU and began placement of SKAPS 330; Completed excavation of SWMU 6 asbestos areas and Area M
Completed deployment of 60 ml geomembrane at south third of CAMU and began placement of SKAPS 220 geocomposite
Continued to deploy 60 ml geomembrane which progressed from SW corner to west slope of CAMU; Excavated Area M asbestos material under supervision of Western AB personnel
Continued to deploy 60 ml geomembrane at SW corner of CAMU
Too windy to deploy 60 ml geomembrane; Continued hauling waste from SWMU 7 SWRP and SWMU 6;
Limited work crew disced and compacted southwest face of CAMU and dewatered SWMU 7 SWRP;
Continued deployment of 60 ml liner to southwest corner of CAMU;
Continued deployment of 60 ml liner to south section of CAMU; Complete final scraping/excavation of SWRP Cell 3
Began deployment of liner at southeast section of CAMU;
Continue final waste grading and compaction at south section of CAMU; Excavated test pits along CAMU East/SWMU 6 fenceline;
No waste hauled to CAMU due to rain; Continued final scraping/excavation of SWRP Cell 3; Grade and compact CAMU surface
Begin final scraping/excavation of SWRP Cell 3; Finish SWMU 6 Haul Rd Excavation
Grade and compact CAMU waste; Worked until 3:30; No work tomorrow
Intermittent rain all day; Grade and compact CAMU waste
Completed final scraping/excavation of Cell 2 of SWRP and collected bottem sample
Continue CAMU preparation at south end for liner; Continue final scraping/excavation of Cell 2 of SWRP
Transport Sludge from SWRP Final Excavation and Scraping Activities to Loadout Area and Haul to CAMU; Continue Excavation of Haul Rd in SWMU 6
Remove material containing asbestos to roll off containers in SWMU 6
Continue SWRP Final Excavation and Scraping Activities in Area 3; Prepare South Area of CAMU for Liner
Continue SWRP Final Excavation and Scraping Activities in Areas 2 and 3; Prepare South Area of CAMU for Liner
Continue SWRP Final Excavation and Scraping Activities in Areas 2 and 3; Prepare South Area of CAMU for Liner
Continue SWRP Final Excavation and Scraping Activities; Prepare South Area of CAMU for Liner
Completed final scraping in Area 1.
Continue surface preparation in CAMU. Move sludge from EQB to load out area in SWRP.
Continue excavation of Area 1.
Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7; Begin excavating and scraping Area 1 of SWRP to grade
Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7
Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7
Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7
Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7
Limited work crew on-site to add/blend LKD in SWRP and EQB
Resume hauling activities from SWMU 6 and SWMU 7
Dewater work areas after heavy rain.
Repair site following rain. Excavate haul road in SWMU 6 near marketing terminal entrance.
Excavation in SWMU 6 at North Perimeter (outside former fenceline).
Excavation in SWMU 6 at North Perimeter. Encountered deeper area of waste.
Continue CAMU Waste Management and Excavation in SWMU 6 at North Perimeter (outside former fenceline)
Continued excavation in SWMU 6 and SWMU 7; Envirocon to take day off tomorrow (Saturday March 5, 2011)
Continued excavation in SWMU 6 and SWMU 7
Continued excavation in SWMU 6, SWMU 7, and AOC 1
Excavation in AOC 1 only due to wet conditions
Continue excavation of SWMU 6 and AOC 1
Began potholing and excavation of AOC 1
No excavation and/or hauling activities conducted; 1/2 day due to rain
Continued SWMU 6 excavation and began east perimeter ditch of CAMU;
Continued SWMU 6 excavation and south perimeter ditch of CAMU;
Continued SWMU 6 excavation and south perimeter ditch of CAMU;
Continued SWMU 6 excavation and began excavating CAMU south perimeter ditch;
Finish SWMU 10 excavtion;
Continue Waste placement from SWMU 6 and SWMU 10;
Continue Waste placement from SWMU 6 and SWMU 10;
Continue Waste placement from SWMU 6 and SWMU 10;
Continue Waste placement from SWMU 6 and SWMU 10;
Continue Waste placement from SWMU 6 and SWMU 10;
Continue Waste placement from SWMU 6; Resume excavation activities at SWMU 10
Continue Waste placement from SWMU 6; Begin installation of new fence at SWMU 6
Limited day due to snow; 1/2 day of dewatering and decon activities;
Excavate and haul from SWMU 6; Begin addition of LKD to west section of EQB;
Excavate and haul from SWMU 6; Constructed access ramp from SWRP to CAMU;
Excavate and haul from SWMU 6 and SWMU 10 (severed power cable in SWMU 10; work ceased); Potholed outside SWMU 6 fenceline between BCP and Area M;
No waste hauled to CAMU; 1/2 work day due to heavy rain;
Continued excavation and hauling out of SWMU 6
Conducted potholing activities outside of fenceline at SWMU 6
Limited work due to rain; Dewatered work areas
Begin demolition of EQB concrete pump structure; Continue backfilling FBP and excavation at SWMU 6
Continue to backfill FBP; Load and haul concrete debris from SWMU 10 to CAMU;
Finalize FBP excavation and begin backfill activities;
Continue excavation of FBP and collect post excavation samples;
Continue excavation of FBP; Begin demolition of concrete pad at SWMU 10;
Rain Day; Dewater Work Areas
Continue adding/mixing LKD into SWRP; Continue excavation of FBP area
Continue adding/mixing LKD into SWRP; Continue excavation of FBP area
Continue adding/mixing LKD into SWRP; Begin excavation of FBP area
Continue adding/mixing LKD into SWRP; Continue demo of FBP berms and pump structure
Continue adding/mixing LKD into SWRP; Continue demo of FBP berms and pump platform
Begin closure of FBP mixing area by pushing in berms and demolition of pump platform
Dewater work areas and repair haul roads after rains last evening
Backfill SWMU 9; Continue excavation and hauling activities in SWMU 6; Prepare for forecasted rain
Backfill SWMU 9; Continue excavation and hauling activities in SWMU 6;
Backfill SWMU 9; Continue excavation and hauling activities in SWMU 6;
Backfill SWMU 9; Continue excavation and hauling activities in SWMU 6;
Backfill SWMU 9; Excavation and Hauling activities in SWMU 6; Begin addition of LKD directly to SWRP
Backfill SWMU 9; Prepare for excavation activities in SWMU 6
Backfill SWMU 9; Dewater and clear trees from SWMU 6
Backfill SWMU 9; Dewater Area A and clear trees from SWMU 6
Complete excavation activities at SWMU 9 and begin backfilling
Continue waste placement and management at CAMU from SWMU 7 and SWMU 9; Evanco completed OWS Cleaning and Inspection Scope of Work
Continue waste placement and management at CAMU from SWMU 7 and SWMU 9;
Continue waste placement and management at CAMU from SWMU 7 and SWMU 9;
Return from holiday downtime; Dewater work areas and disc/grade CAMU
Clean up and prepare site for holiday downtime; Will resume work January 3, 2011
Continue Waste Placement in CAMU from SWMU 7 and 9; Evanco completed cleaning and inspection of OWS-1A (ASB58 to SB60)
Continue Waste Placement in CAMU from SWMU 7 and 9; Evanco completed cleaning and inspection of OWS Sump and OWS Sump to SB42
Limited Envirocon crew conducted pumping/solidification at SWMU 7; Evanco continued cleaning from OWS Sump to SB42
Continue Waste Placement in CAMU from SWMU 7 and 9; Evanco continued cleaning from OWS Sump to SB42
Snow and ice clean up; Hauled waste from FBP to CAMU; Evanco conducted initial cleaning of OWS-1A from SB60
Continue Waste Placement in CAMU from SWMU 7 and 9; Early shutdown due to snow;
Continue Waste Placement in CAMU from SWMU 7 and 9; Evanco continued cleaning and inspection at OWS Sump, SB41, and SB42
Continue Waste Placement in CAMU from SWMU 7 and 9; Evanco continued cleaning and inspection at OWS Sump, SB41, and SB42
Manage Waste in CAMU and Dewater SWMUs after rain event; Evanco continued cleaning OWS Sump
Continue Excavation of SWMU 9; Limited Evanco crew began laydown/set up of by pass line from SB58 to SB59
Continue Excavation of SWMU 9; Evanco began cleaning of OWS Sump to SB41
Continue Excavation of SWMU 9;
Continue Excavation of SWMU 9;
Continue Excavation of SWMU 9;
Continue Excavation of SWMU 9;
Continue Excavation of SWMU 9;
Continue Excavation of SWMU 9; Evanco completed final CCTV of SB37 to SB40 and SB35 to SB37
Continue Excavation of SWMU 9; Evanco continued cleaning SB37 to SB40
Limited Work day due to Weather;
Began SWMU 9 Excavation;
Prepared for SWMU 9 Excavation;
Cleaned and secured work areas for Thanksgiving Holiday;
Continued waste management in CAMU West; Evanco continued cleaning from SB35 to SB37;
Continued waste placement/management in CAMU West from SWMU 7 and SWMU 6 Area F overexcavation; Evanco began cleaning from SB35 to SB37;
Cleaned east/west 6" OWS line in SWMU 5N;
Continue waste placement/management in CAMU West from SWMU 7 and SWMU 6 Area C Overexcavation; Evanco completed cleaning and CCTV Inspection from SB10 to SB35;
Continue waste placement/management in CAMU West from SWMU 7 and SWMU 6 Area D; Evanco continued cleaning from SB10 to SB35
Continue waste placement/management in CAMU West from SWMU 7 and SWMU 6 Area D; Evanco continued cleaning from SB10 to SB35
Continue waste placement/management in CAMU West from SWMU 7 and SWMU 6 Areas K and L; Evanco continued cleaning from SB10 to SB35
Continue waste placement/management in CAMU West from SWMU 6 Areas K and L; Evanco began cleaning from SB10 to SB35
Continue waste placement/management in CAMU West from SWMU 7; Evanco not onsite
Continue waste placement/management in CAMU West from SWMU 6 Areas I and J; Evanco completed cleaning and final CCTV inspectin from SB7 to SB10
Continue waste placement/management in CAMU West from SWMU 6 and SWMU 7; Evanco cleaning SB7 to SB10
Continue waste placement/management in CAMU West from SWMU 6 and SWMU 7; Evanco completed final CCTV from SB6 to SB7
Continue waste placement/management in CAMU West from SWMU 6, SWMU 5N, and SWMU 7; Evanco finished cleaning from SB6 to SB7
Continue waste placement/management in CAMU West from SWMU 6, SWMU 5N, and SWMU 7; Evanco continued cleaning from SB6 to SB7
Limited Envirocon crew onsite for equipment maintenance and accepting LKD deliveries; Evanco not onsite
Continued dewatering of excavation areas after rain; Evanco continued to clean SB6 to SB7
Envirocon dewatered excavation areas after rain; Evanco continued to clean SB6 to SB7
Removed remainder of 24" Spillway in south wall of SWMU 5N excavation (leftover from Phase I CMI activities; Evanco continued to clean SB6 to SB7
Continued Waste Placement Activities from SWMU 6 and SWMU 7; Removed 6" OWS line from SWMU 5N; Evanco continued to clean SB6 to SB7
Continued Waste Placement Activities from SWMU 6 and SWMU 7; Evanco continued to clean SB6 to SB7
Limited work; Continued trial testing modified LKD delivery method;
Continued dewatering activities; Decon sheetpile; Trial tested modified LKD delivery method; Evanco continued to clean SB6 to SB7;
Limited work due to heavy rain; Dewatering of SWMU 6 and SWMU 5N excavations;
Excavated 24" spillway from SWMU 5N;
Excavated 2-6" and 2-16" pipes from SWMU 5N;
Began excavation of Areas G and F in SWMU 6; Collected verification samples from Areas A, B, C in SWMU 6;
Removed Transite pipe from SWMU 5N; Began excavation Area A and M in SWMU 6;
Completing excavation activities in SWMU 5N and continued excavation of Area C and B in SWMU 6; Evanco delivered 16yds material to FBP N mixing cell;
Begin Excavation of Area C and B in SWMU 6;
Continued excavation in SWMU 5N;
Excavated CW312 area in SWMU 5N
Continued Waste Placement activities in CAMU W (from SWMU 5N and SWMU 7)
Conducted CAMU West Waste Management activities by discing, rolling, and grading material from SWMU 5N and SWMU 7
Continued Waste Placement Activities in CAMU W and Review of Pilot Study Report; Continued OWS CIR Activities
Continued Waste Placement Activities in CAMU W and Review of Pilot Study Report; Continued OWS CIR Activities
Continued Waste Placement Activities in CAMU W and Preparation of Pilot Study Report; Continued OWS CIR Activities
Continued Waste Placement Activities in CAMU W and Preparation of Pilot Study Report; Continued OWS CIR Activities
Hauled and Placed N Mixing Cell of FBP into CAMU Test Pads as Part of Final Phase 3 Pilot Study; Continued OWS CIR Activities
Filled N Mixing Cell of FBP as Part of Final Phase 3 Pilot Study; No OWS CIR Work Conducted
Envirocon Tested Methods for Adding LKD Reagent with Minimal Dust; Resume Inspection from SB1 to Tank 10 and Begin Cleaning from SB1 to SB2;
Continue Dewatering Phase II CMI Work Areas; Continue OWS CIR from SB1 to Tank 900
Continue Dewatering Phase II CMI Work Areas; Begin OWS CIR from SB1 to Tank 10
Continue Dewatering Phase II CMI Work Areas
Continue Dewatering Phase II CMI Work Areas
Begin 24 Hour Dewatering of Work Areas
Set Up Pumps and Prepare to Dewater Work Areas
Inspection of Storm Water E&S Controls
Phase II CMI Activities Limited Due to Heavy Rain
Prepare for Forecasted Tropical Storm Weather Front
Evanco Continues Installation of Bypass Manifold; Mix Test Batches of Sludge as Part of Phase 3 Pilot Study
Continue Revised Phase 3 of Pilot Study; Evanco Begins Installation of Bypass Manifold.
Continue SWMU 5N Excavation; Continue Revised Phase 3 of Pilot Study.
Continue SWMU 5N Excavation; Resume OWS-C East Excavation; Begin Revised Phase 3 of Pilot Study.
Continue SWMU 5N Excavation.
Beginning of SWMU 5 N Excavation.
Continue Excavation and Removal OWS-C East.
Continue Excavation and Removal OWS-C East.
Continue Excavation and Removal OWS-C East.
Begin Excavation and Removal OWS-C East.
Complete Cleaning of OWS-C East; Continued Excavation of SWMU 2.
Partial Sampling Conducted in SWMU 2; Continued Cleaning of OWS-C East.
Continued Excavation of SWMU 2; Cleaning of OWS-C East.
Day 22 Pilot Study.
Day 21 Pilot Study.
Day 20 Pilot Study.
Day 19 of Pilot Study.
Day 18 Initiate Dredge Phase III of Pilot Study.
Day 17 of Pilot Study.
Day 16 Initiate Dredge Phase III of Pilot Study.
Day 15 of Pilot Study.
Day 14 of Pilot Study.
Day 13 of Pilot Study.
Day 12 of Pilot Study.
Day 11 of Pilot Study.
Day Ten of Pilot Study.
Day Nine of Pilot Study.
Day Eight of Pilot Study.
Day Seven of Pilot Study.
Day Six of Pilot Study.
Day Five of Stage 1 Pilot Study.
Day Four of Stage 1 Pilot Study.
Day Three of Stage 1 Pilot Study.
Day Two of Stage 1 Pilot Study.
Day One of Stage 1 Pilot Study.
Prepare for Stage 1 of Pilot Study.
Topo survey of SWRP TSWRB 40ml liner delivered to site.
Place Dredge into SWRP Continue CAMU Berms and Access Egress Ramps.
Set Up and Calibrate Survey Equipment for Dredge.
Dredge Mobilized to Site RFIs and Transmittals Attached.
Begin welding HDPE for upcoming dredge operations.
Continued preparation CAMU berms and TSWRB.
Complete final SWMU 8 hot spot excavation.
Continued Excavation SWMU 8.
Begin SWMU 8 Excavation and N Berm Construction.
Continued Excavation TSWRB.
Continued Excavation TSWRB.
Backfill C6 Excavation.
Complete C6 NAPL Excavation.
Began C-6 NAPL Area excavation.
Began construction of TSWRB.
Surveyed boundaries for SWMU 9, 10, 8.
Began construction of South berm of Temporary Stormwater Retention Basin.
Chipping in SWMU 2 begins.
Began preparing CAMU West test pad area.
Proof rolling in CAMU West. Clearing SWMU 2 continues.
Clearing CAMU West. Clearing SWMU 2 begins.
Clearing CAMU West.
Surveying CAMU West.
Clearing and Surveying CAMU West.
Continue Clearing SWMU 5 North and SWMU 6.
Access Road and locate SWMU 6 excavation areas.
SWMU 5 and SWMU 6 mowing.
Background PAMP monitoring.
Background PAMP monitoring.
Clearing and surveying of SWMU 6. Background PAMP monitoring.
Clearing and surveying of SWMU 6. Background PAMP monitoring.
Surveyors begin work.
Envirocon work crew begin site orientation.
PAMP monitoring stations were installed.