Limited work; Continued trial testing modified LKD delivery method;
Continued dewatering activities; Decon sheetpile; Trial tested modified LKD delivery method; Evanco continued to clean SB6 to SB7;
Limited work due to heavy rain; Dewatering of SWMU 6 and SWMU 5N excavations;
Excavated 24" spillway from SWMU 5N;
Excavated 2-6" and 2-16" pipes from SWMU 5N;
Began excavation of Areas G and F in SWMU 6; Collected verification samples from Areas A, B, C in SWMU 6;
Removed Transite pipe from SWMU 5N; Began excavation Area A and M in SWMU 6;
Completing excavation activities in SWMU 5N and continued excavation of Area C and B in SWMU 6; Evanco delivered 16yds material to FBP N mixing cell;
Begin Excavation of Area C and B in SWMU 6;
Continued excavation in SWMU 5N;
Excavated CW312 area in SWMU 5N
Continued Waste Placement activities in CAMU W (from SWMU 5N and SWMU 7)
Conducted CAMU West Waste Management activities by discing, rolling, and grading material from SWMU 5N and SWMU 7
Continued Waste Placement Activities in CAMU W and Review of Pilot Study Report; Continued OWS CIR Activities
Continued Waste Placement Activities in CAMU W and Review of Pilot Study Report; Continued OWS CIR Activities
Continued Waste Placement Activities in CAMU W and Preparation of Pilot Study Report; Continued OWS CIR Activities
Continued Waste Placement Activities in CAMU W and Preparation of Pilot Study Report; Continued OWS CIR Activities
Hauled and Placed N Mixing Cell of FBP into CAMU Test Pads as Part of Final Phase 3 Pilot Study; Continued OWS CIR Activities
Filled N Mixing Cell of FBP as Part of Final Phase 3 Pilot Study; No OWS CIR Work Conducted
Envirocon Tested Methods for Adding LKD Reagent with Minimal Dust; Resume Inspection from SB1 to Tank 10 and Begin Cleaning from SB1 to SB2;
Continue Dewatering Phase II CMI Work Areas; Continue OWS CIR from SB1 to Tank 900
Continue Dewatering Phase II CMI Work Areas; Begin OWS CIR from SB1 to Tank 10
Continue Dewatering Phase II CMI Work Areas
Continue Dewatering Phase II CMI Work Areas
Begin 24 Hour Dewatering of Work Areas
Set Up Pumps and Prepare to Dewater Work Areas
Inspection of Storm Water E&S Controls