Posted February 8, 2011 Daily Report for Monday January 31, 2011

Continue to backfill FBP; Load and haul concrete debris from SWMU 10 to CAMU;


Posted February 2, 2011 Daily Report for Saturday January 29, 2011

Finalize FBP excavation and begin backfill activities;


Posted February 2, 2011 Daily Report for Friday January 28, 2011

Continue excavation of FBP and collect post excavation samples;


Posted February 2, 2011 Daily Report for Thursday January 27, 2011

Continue excavation of FBP; Begin demolition of concrete pad at SWMU 10;


Posted February 2, 2011 Daily Report for Wednesday January 26, 2011

Rain Day; Dewater Work Areas


Posted January 26, 2011 Daily Report for Tuesday January 25, 2011

Continue adding/mixing LKD into SWRP; Continue excavation of FBP area


Posted January 26, 2011 Daily Report for Monday January 24, 2011

Continue adding/mixing LKD into SWRP; Continue excavation of FBP area


Posted January 25, 2011 Daily Report for Saturday January 22, 2011

Continue adding/mixing LKD into SWRP; Begin excavation of FBP area


Posted January 25, 2011 Daily Report for Friday January 21, 2011

Continue adding/mixing LKD into SWRP; Continue demo of FBP berms and pump structure


Posted January 25, 2011 Daily Report for Thursday January 20, 2011

Continue adding/mixing LKD into SWRP; Continue demo of FBP berms and pump platform


Posted January 21, 2011 Daily Report for Wednesday January 19, 2011

Begin closure of FBP mixing area by pushing in berms and demolition of pump platform


Posted January 21, 2011 Daily Report for Tuesday January 18, 2011

Dewater work areas and repair haul roads after rains last evening


Posted January 21, 2011 Daily Report for Monday January 17, 2011

Backfill SWMU 9; Continue excavation and hauling activities in SWMU 6; Prepare for forecasted rain


Posted January 21, 2011 Daily Report for Saturday January 15, 2011

Backfill SWMU 9; Continue excavation and hauling activities in SWMU 6;


Posted January 17, 2011 Daily Report for Friday January 14, 2011

Backfill SWMU 9; Continue excavation and hauling activities in SWMU 6;


Posted January 17, 2011 Daily Report for Thursday January 13, 2011

Backfill SWMU 9; Continue excavation and hauling activities in SWMU 6;


Posted January 17, 2011 Daily Report for Wednesday January 12, 2011

Backfill SWMU 9; Excavation and Hauling activities in SWMU 6; Begin addition of LKD directly to SWRP


Posted January 14, 2011 Daily Report for Tuesday January 11, 2011

Backfill SWMU 9; Prepare for excavation activities in SWMU 6


Posted January 14, 2011 Daily Report for Monday January 10, 2011

Backfill SWMU 9; Dewater and clear trees from SWMU 6


Posted January 11, 2011 Daily Report for Saturday January 8, 2011

Backfill SWMU 9; Dewater Area A and clear trees from SWMU 6


Posted January 11, 2011 Daily Report for Friday January 7, 2011

Complete excavation activities at SWMU 9 and begin backfilling


Posted January 10, 2011 Daily Report for Thursday January 6, 2011

Continue waste placement and management at CAMU from SWMU 7 and SWMU 9; Evanco completed OWS Cleaning and Inspection Scope of Work


Posted January 7, 2011 Daily Report for Wednesday January 5, 2011

Continue waste placement and management at CAMU from SWMU 7 and SWMU 9;


Posted January 7, 2011 Daily Report for Tuesday January 4, 2011

Continue waste placement and management at CAMU from SWMU 7 and SWMU 9;


Posted January 7, 2011 Daily Report for Monday January 3, 2011

Return from holiday downtime; Dewater work areas and disc/grade CAMU