June July August September October November December January February March April May June July


August 02, 2010 10 07 31 Daily Report

Continued Excavation TSWRB.


August 02, 2010 10 07 30 Daily Report

Backfill C6 Excavation.


August 02, 2010 10 07 29 Daily Report

Complete C6 NAPL Excavation.


July 29, 2010 10 07 28 Daily Report

Began C-6 NAPL Area excavation.


July 29, 2010 10 07 27 Daily Report

Began construction of TSWRB.


July 27, 2010 10 07 26 Daily Report

Surveyed boundaries for SWMU 9, 10, 8.


July 26, 2010 10 07 23 Daily Report

Began construction of South berm of Temporary Stormwater Retention Basin.


July 23, 2010 10 07 22 Daily Report

Chipping in SWMU 2 begins.


July 22, 2010 10 07 21 Daily Report

Began preparing CAMU West test pad area.


July 22, 2010 10 07 20 Daily Report

Proof rolling in CAMU West. Clearing SWMU 2 continues.


July 20, 2010 10 07 19 Daily Report

Clearing CAMU West. Clearing SWMU 2 begins.


July 20, 2010 10 07 17 Daily Report

Clearing CAMU West.


July 19, 2010 10 07 16 Daily Report

Surveying CAMU West.


July 16, 2010 10 07 15 Daily Report

Clearing and Surveying CAMU West.


July 16, 2010 10 07 14 Daily Report

Continue Clearing SWMU 5 North and SWMU 6.


July 13, 2010 10 07 13 Daily Report

Access Road and locate SWMU 6 excavation areas.


July 12, 2010 10 07 12 Daily Report

SWMU 5 and SWMU 6 mowing.


July 11, 2010 10 07 11 Daily Report

Background PAMP monitoring.


July 10, 2010 10 07 10 Daily Report

Background PAMP monitoring.


July 9, 2010 10 07 09 Daily Report

Clearing and surveying of SWMU 6. Background PAMP monitoring.


July 8, 2010 10 07 08 Daily Report

Clearing and surveying of SWMU 6. Background PAMP monitoring.


July 7, 2010 10 07 07 Daily Report

Surveyors begin work.


July 6, 2010 10 07 06 Daily Report

Envirocon work crew begin site orientation.