Posted April 3, 2011 Daily Report for Thursday March 31, 2011

Intermittent rain all day; Grade and compact CAMU waste


Posted April 3, 2011 Daily Report for Wednesday March 30, 2011

Completed final scraping/excavation of Cell 2 of SWRP and collected bottem sample


Posted April 3, 2011 Daily Report for Tuesday March 29, 2011

Continue CAMU preparation at south end for liner; Continue final scraping/excavation of Cell 2 of SWRP


Posted March 29, 2011 Daily Report for Monday March 28, 2011

Transport Sludge from SWRP Final Excavation and Scraping Activities to Loadout Area and Haul to CAMU; Continue Excavation of Haul Rd in SWMU 6


Posted March 28, 2011 Daily Report for Saturday March 26, 2011

Remove material containing asbestos to roll off containers in SWMU 6


Posted March 28, 2011 Daily Report for Friday March 25, 2011

Continue SWRP Final Excavation and Scraping Activities in Area 3; Prepare South Area of CAMU for Liner


Posted March 28, 2011 Daily Report for Thursday March 24, 2011

Continue SWRP Final Excavation and Scraping Activities in Areas 2 and 3; Prepare South Area of CAMU for Liner


Posted March 25, 2011 Daily Report for Wednesday March 23, 2011

Continue SWRP Final Excavation and Scraping Activities in Areas 2 and 3; Prepare South Area of CAMU for Liner


Posted March 25, 2011 Daily Report for Tuesday March 22, 2011

Continue SWRP Final Excavation and Scraping Activities; Prepare South Area of CAMU for Liner


Posted March 22, 2011 Daily Report for Thursday March 21, 2011

Completed final scraping in Area 1.


Posted March 22, 2011 Daily Report for Thursday March 20, 2011

Continue surface preparation in CAMU. Move sludge from EQB to load out area in SWRP.


Posted March 22, 2011 Daily Report for Thursday March 19, 2011

Continue excavation of Area 1.


Posted March 21, 2011 Daily Report for Thursday March 18, 2011

Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7; Begin excavating and scraping Area 1 of SWRP to grade


Posted March 21, 2011 Daily Report for Thursday March 17, 2011

Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7


Posted March 18, 2011 Daily Report for Wednesday March 16, 2011

Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7


Posted March 18, 2011 Daily Report for Tuesday March 15, 2011

Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7


Posted March 16, 2011 Daily Report for Monday March 14, 2011

Continue waste placement in CAMU from AOC 1, SWMU 6, and SWMU 7


Posted March 15, 2011 Daily Report for Sunday March 13, 2011

Limited work crew on-site to add/blend LKD in SWRP and EQB


Posted March 15, 2011 Daily Report for Saturday March 12, 2011

Resume hauling activities from SWMU 6 and SWMU 7


Posted March 15, 2011 Daily Report for Friday March 11, 2011

Dewater work areas after heavy rain.


Posted March 14, 2011 Daily Report for Thursday March 10, 2011

Repair site following rain. Excavate haul road in SWMU 6 near marketing terminal entrance.


Posted March 10, 2011 Daily Report for Wednesday March 9, 2011

Excavation in SWMU 6 at North Perimeter (outside former fenceline).


Posted March 10, 2011 Daily Report for Tuesday March 8, 2011

Excavation in SWMU 6 at North Perimeter. Encountered deeper area of waste.


Posted March 9, 2011 Daily Report for Monday March 7, 2011

Continue CAMU Waste Management and Excavation in SWMU 6 at North Perimeter (outside former fenceline)


Posted March 7, 2011 Daily Report for Friday March 4, 2011

Continued excavation in SWMU 6 and SWMU 7; Envirocon to take day off tomorrow (Saturday March 5, 2011)


Posted March 7, 2011 Daily Report for Thursday March 3, 2011

Continued excavation in SWMU 6 and SWMU 7


Posted March 3, 2011 Daily Report for Wednesday March 2, 2011

Continued excavation in SWMU 6, SWMU 7, and AOC 1


Posted March 3, 2011 Daily Report for Tuesday March 1, 2011

Excavation in AOC 1 only due to wet conditions