Began SWMU 9 Excavation;
Prepared for SWMU 9 Excavation;
Cleaned and secured work areas for Thanksgiving Holiday;
Continued waste management in CAMU West; Evanco continued cleaning from SB35 to SB37;
Continued waste placement/management in CAMU West from SWMU 7 and SWMU 6 Area F overexcavation; Evanco began cleaning from SB35 to SB37;
Cleaned east/west 6" OWS line in SWMU 5N;
Continue waste placement/management in CAMU West from SWMU 7 and SWMU 6 Area C Overexcavation; Evanco completed cleaning and CCTV Inspection from SB10 to SB35;
Continue waste placement/management in CAMU West from SWMU 7 and SWMU 6 Area D; Evanco continued cleaning from SB10 to SB35
Continue waste placement/management in CAMU West from SWMU 7 and SWMU 6 Area D; Evanco continued cleaning from SB10 to SB35
Continue waste placement/management in CAMU West from SWMU 7 and SWMU 6 Areas K and L; Evanco continued cleaning from SB10 to SB35
Continue waste placement/management in CAMU West from SWMU 6 Areas K and L; Evanco began cleaning from SB10 to SB35
Continue waste placement/management in CAMU West from SWMU 7; Evanco not onsite
Continue waste placement/management in CAMU West from SWMU 6 Areas I and J; Evanco completed cleaning and final CCTV inspectin from SB7 to SB10
Continue waste placement/management in CAMU West from SWMU 6 and SWMU 7; Evanco cleaning SB7 to SB10
Continue waste placement/management in CAMU West from SWMU 6 and SWMU 7; Evanco completed final CCTV from SB6 to SB7
Continue waste placement/management in CAMU West from SWMU 6, SWMU 5N, and SWMU 7; Evanco finished cleaning from SB6 to SB7
Continue waste placement/management in CAMU West from SWMU 6, SWMU 5N, and SWMU 7; Evanco continued cleaning from SB6 to SB7
Limited Envirocon crew onsite for equipment maintenance and accepting LKD deliveries; Evanco not onsite
Continued dewatering of excavation areas after rain; Evanco continued to clean SB6 to SB7
Envirocon dewatered excavation areas after rain; Evanco continued to clean SB6 to SB7
Removed remainder of 24" Spillway in south wall of SWMU 5N excavation (leftover from Phase I CMI activities; Evanco continued to clean SB6 to SB7
Continued Waste Placement Activities from SWMU 6 and SWMU 7; Removed 6" OWS line from SWMU 5N; Evanco continued to clean SB6 to SB7
Continued Waste Placement Activities from SWMU 6 and SWMU 7; Evanco continued to clean SB6 to SB7